In image: Regional Project Monitoring Committee XI monitoring team inspects the tunnel along Package I-1 of the Davao City Bypass Construction Project during the RPMC XI 4th Quarter 2026 field monitoring activity on October 13, 2026

(Davao City, October 15, 2026). The Regional Project Monitoring Committee (RPMC) XI conducted its 4th Quarter 2026 Field Validation Activity on October 13–15, 2026, to assess the implementation progress and address concerns affecting three major infrastructure projects in the Davao Region: the Davao City Bypass Construction Project (DCBCP), Samal Island–Davao City Connector (SIDC) Project, and Mati Airport Development Project. The activity also included monitoring of projects with negative slippages identified in the 2nd Quarter 2026 Regional Project Monitoring and Evaluation System (RPMES) reports.

The Davao City Bypass Construction Project, a 45.5-kilometer road network connecting Toril, Davao City, and Panabo City, recorded 44.15 percent physical accomplishment as of September 30, 2026. Ongoing works include tunnel and bridge construction, earthworks, pavement construction, and drainage installation across five (5) project contract packages.

The Samal Island–Davao City Connector Project involves the construction of a 3.98-kilometer extradosed bridge connecting Davao City and the Island Garden City of Samal. As of September 25, 2026, it recorded 65.42 percent actual accomplishment against a scheduled 63.33 percent, reflecting a positive slippage of 2.09 percentage points. Ongoing works include bridge pier and superstructure construction, pile cap and pier column concreting, and land and marine viaduct works. Right-of-way acquisition and utility concerns remain under monitoring. Meanwhile, the Economy and Development Council has approved the project’s restructuring, as endorsed by the Regional Development Council (RDC) XI. The restructuring covers changes in project scope, cost, financing, and implementation period, including an increase in the total project cost and an extension of the completion date.

The Mati Airport Development Project continues to target turboprop operations by the fourth quarter of 2027. The passenger terminal building expansion and construction of auxiliary facilities recorded 47.38 percent accomplishment against a planned 53.40 percent, or a negative slippage of 6.02 percentage points. Construction is partially suspended pending the processing of demolition and building permits. Meanwhile, the rehabilitation of the runway, apron, and taxiways, and the construction of a control tower require additional funding to pursue wide and narrow-bodied commercial flight operations. Right-of-way-related survey and land title concerns also remain under coordination with concerned agencies.

Through the field validation, the RPMC XI assessed project accomplishments, identified implementation bottlenecks, and strengthened coordination with implementing agencies to help address delays and advance the completion of priority infrastructure projects that support connectivity and economic growth in the Davao Region.

 